Home > Uncategorized > Updating Progress in MS Project

Updating Progress in MS Project

Let’s assume you are one of many that use MS Project to develop a nice neat plan in order to begin a project.  However, once the work starts you find the tool cumbersome to update the plan.  You promise yourself you will take a class one day on how to update MS Project with actuals, but right now you need to show the progress performed.  Below are some simple ways to do this.  (I still recommend a class when you have the time!)

As you attempt to catch-up with the work performed on the project and reflect it in the plan, the first thing to do is set the Status Date of the project. This is located in the Project Menu>>Project Information option.  Setting this is key to a number of different functions in MS Project, however we are keeping things simple today, so let’s do this.  Assume the status date is the current date.

Project info

Next thing I like to do is see the status date visually on the Tracking Gantt Chart.  In order to do this, select the format option from the menu and select Grid lines.  In the lines to change area, select “Status Date” and on the right side of the window choose the type and color of the line you would like to see.

Status date

Once you click OK, a vertical line appears on your Tracking Gantt chart to show the status date.  Last but not least, enable the tracking toolbar.

Satus date gantt

Now you are ready for the easy updates you were looking for.  There are multiple options to perform the tracking depending on how detailed you want to go, but I will explain 2 of the methods I have used most.

Method 1:  The easiest method if all is going well.  Simply select the task/s you would like to update and the click on the option off the tracking toolbar to “Update as Scheduled” this will update the task as complete through the Status Date.

Updateas schedule

Method 2:  This is a bit more complex, but easier as you get the hang of it.  If some of the work is complete, but not all, update the portion of work that is complete using the % complete buttons on the tracking toolbar.  Now the remainder of the work that is not complete must be rescheduled, so click on the task and then select the reschedule work option.   This will move the incomplete portion of the work after the status date.  This makes sense since you cannot complete the work in the past.  (Caution, if you have setup your network diagram properly the remainder of the schedule could change)

rescheduled

Simple techniques make all the difference in gaining efficiencies for the Project Manager.

Happy tracking!

Advertisement
Categories: Uncategorized Tags: ,
  1. March 29, 2011 at 5:24 pm | #1

    I used to use MSProject about 10 or 15 years ago. It had a nice feature that I could schedule an email to be sent to the resources showing last week’s percent complete and gave them cells to put this weeks percent complete and send it right bact to me. Then I could accept the updated percentages with just a click or reject them just as simply. It made updating the percentage complete status weekly a very easy thing. I am trying to set up an new project schedule the same way. However, I am having a little trouble setting this up on MSProject 2010. Can I still do this with the newer MSProject?

    • Pete
      March 30, 2011 at 6:51 am | #2

      I will be honest with you I have not tried to do this in MS Project 2010 as it is so closely integrated with Project Server that my preferred usage of the tool now. I have tried to use this in prior versions of MS Project, but have always had trouble with the implementation as it required add ins to MS Office and was a bit buggy. My recommendation is to post your question out on one of the project message boards to see if anyone has had any luck with this. My assumption is the standard answer will be you should use MS Project Server.

      I always use http://groups.google.com/group/microsoft.public.project/ to get answers. Very good site.

      Good luck.

  1. No trackbacks yet.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Connecting to %s

Follow

Get every new post delivered to your Inbox.